Quick answer

In redevelopment, the society or owners give a developer the right to demolish and rebuild, in exchange for new flats, transit rent and a corpus. In Maharashtra, cooperative societies must follow the government directives under Section 79A of the Cooperative Societies Act, with majority approval at a special general meeting. Every member should sign a registered permanent alternate accommodation agreement. If the builder delays or abandons the project, the society can terminate, claim compensation, and approach the arbitrator, RERA or the court.

Who decides whether a building goes for redevelopment

The answer depends on what kind of building you live in:

  • Cooperative housing society (Maharashtra): the decision is taken under the directives issued under Section 79A of the Maharashtra Cooperative Societies Act. These require a structural audit or reason, a special general body meeting with a set quorum, approval by a majority of members as the directives prescribe, appointment of a project management consultant, and open tendering for the developer. A meeting held without proper notice can be challenged before the Registrar.
  • Apartment owners' association or a building without a society: usually every owner's consent is needed, since each owns an undivided share in land.
  • Old cessed buildings with landlord and tenants: MHADA laws and the landlord's ownership both come in; tenants' consent and rehabilitation entitlements are statutory.
  • Slums: the Slum Rehabilitation Authority governs, with its own eligibility rules.

Minority who refuse: two shopkeepers out of 27 cannot usually block a properly passed redevelopment. Bombay High Court decisions have repeatedly ordered non-cooperating members to vacate where the society's decision was lawful and their entitlements were equal to others'. But a dissenter can genuinely succeed if the meeting was flawed or they are being offered less than the others.

The agreements, and what each must say

Development Agreement (DA): between society and developer, with a power of attorney for approvals. It must be stamped and registered. Check:

  • Additional carpet area per member (for example 30% to 40% more than existing, depending on FSI available)
  • Monthly transit rent, with escalation, and brokerage and shifting charges
  • Corpus fund per member, and when it is paid
  • Completion period (often 24 to 36 months from commencement certificate), with a penalty per month of delay
  • Bank guarantee from the developer
  • Right to terminate and an arbitration clause
  • Allotment of flats by lottery or floor-wise matching

Permanent Alternate Accommodation Agreement (PAAA): between each member and developer, identifying the new flat. Get it registered. Without it, you have only the society's general promises. Flat number changes later need your written consent.

Paying for extra area: if you want more than the free entitlement, you buy it at an agreed rate. You cannot be forced to buy it. If the developer demands money for your basic entitlement, refuse in writing.

Title deed: the society hands over title documents to the developer for approvals; members keep their share certificates. Do not give your personal originals unless the agreement requires it, and take a receipt.

Documents members should keep ready: share certificate, original agreement for the existing flat, latest maintenance and property tax receipts, nomination records, and proof of any loan on the flat. If a member has died and heirs have not been admitted to membership, sort that out early; developers will not sign a PAAA with an unrecorded heir, and it can hold up the whole building.

Selling, gifting or mortgaging a flat under redevelopment

You can sell or gift your right to the new flat. The buyer steps into your PAAA and society membership, and the developer's and society's NOC is usually needed. Stamp duty is payable on the transfer. A gift deed to a family member works similarly, though rates differ by state. Banks lending on such a flat want the DA, PAAA, developer NOC and RERA registration of the project.

Watch the POA trap. If you gave a power of attorney to a relative for redevelopment, check its scope. A POA only for signing redevelopment documents does not allow selling the flat; if someone sold under it, the sale can be challenged. See revoking a power of attorney.

When the builder delays, stops or disappears

Stalled redevelopments are the commonest complaint: members out of their homes for years, rent stopped. Steps in order:

  1. Document defaults: list unpaid rent months, missed milestones, and lapsed approvals.
  2. Formal notice: the society sends a default notice under the DA.
  3. Interim relief: under Section 9 of the Arbitration and Conciliation Act, the society or members can ask the court to direct deposit of rent or restrain the builder from selling sale-component flats.
  4. Terminate and appoint a new developer: requires a general body resolution and careful handling of the old developer's claims. Courts may stay termination if the society itself is in breach.
  5. RERA: where the project has a sale component, it must be registered with MahaRERA, and members can complain for delay; see RERA vs consumer forum.
  6. Criminal complaint: where money was taken by deceit or flats were sold twice.

Example: suppose a Borivali society's builder stops transit rent after 18 months. The society can seek a Section 9 order directing the builder to deposit rent arrears of, say, ₹1.2 crore, terminate the DA, and appoint a new developer who takes over the liabilities. Such rescues commonly take two to four years.

Tenants in redeveloped buildings

Tenants of old rented buildings, including pagdi tenants, get rehabilitation in the new building rather than cash, unless they choose otherwise. Rent remains payable to the landlord until the agreement shifts it; a landlord cannot ask you to pay rent to the developer unless the agreements say so. A tenant who does not pay rent during the transit period may still face default claims. Pagdi-specific rights are in our guide on the pagdi system.

Buying a hutment going for SRA redevelopment

Very risky. Eligibility under the SRA scheme depends on proof of residence before a cut-off date, and the rehab flat usually cannot be sold or transferred for a lock-in period (commonly 10 years from allotment). A purchase from an eligible slum dweller before allotment often does not give you a rehab flat in your own name. Read the current SRA rules before paying.

If you have already bought such a hutment, keep every proof of the original occupant's eligibility and your payment, and get a registered agreement with the seller recording that the rehab flat will be transferred to you once the lock-in ends. Check with the SRA office whether the annexure II (eligibility list) names the seller.

When the committee is the problem

If committee members took kickbacks, skipped tendering, or hid documents, members can complain to the Deputy Registrar of Cooperative Societies, seek inspection of records under the Act, and file a dispute before the Cooperative Court. General society disputes are discussed in housing society disputes.

Frequently asked questions

Is the society redevelopment agreement required to be registered?

Yes. A development agreement giving rights in immovable property must be stamped and registered, and each member's permanent alternate accommodation agreement should also be registered. An unregistered agreement is hard to enforce.

Can a society go for redevelopment when a court case is pending?

It depends on the case. If there is a stay order, nothing can be done against it. Otherwise the society can proceed, but the developer and bank will want the dispute disclosed and resolved or provided for in the agreements.

Who pays rent if the builder stops paying transit rent?

The builder remains liable under the agreement. The society or member can recover arrears with interest through arbitration or court, and can ask for interim orders directing deposit. Members should not stop pursuing it, because limitation runs.

Can I get a higher floor in redevelopment?

Only if the agreement provides for it or you negotiate and pay a premium. Most agreements allot by lottery or keep members on similar floors. Raise it before the PAAA is signed.

Is corpus fund taxable?

Tax treatment of corpus, hardship allowance and transit rent has been argued before tax tribunals with differing results. Take advice from a chartered accountant on your figures before filing returns.

Talk to an advocate about your case

Every case turns on its own documents and dates. If you want someone to look at yours, you can book a consultation with a verified advocate on Hire Your Vakeel, or browse advocates who handle property law matters.

This guide is general legal information, not legal advice. Laws, fees and portal steps change, so confirm the current position with an advocate before you act.

Need legal help for this matter?

Share your case details and preferred consultation mode. Hire Your Vakeel will help you take the next step with an advocate.

Request advocate consultation